ENTSOG GRIP BEMIP 2014-2023 / Main Report
4.1 Map of Planned
Infrastructure Projects
This chapter provides an outlook of major gas infrastructure development in the BEMIP region until 2025. The projects are presented in a schematic way on the map on the following page. 1)
No. Promoter
Project name
Code 1)
Commissioning
IMPLEMENTATION UP TO 2016 1 GAZ-SYSTEM S.A.
Physical reverse flow on the metering station in Mallnow
TRA-F-326
2013
2 Energinet.dk
Ellund-Egtved
TRA-F-015
2013
3 PGNiG
PMG Husów
UGS-F-202
2014
4 PGNiG
PMG Wierzchowice
UGS-F-220
2014
5 Maersk Oil and Gas AS
Tie-in of Norwegian off-shore natural gas transmission system to Danish off-shore natural gas infrastructure
TRA-N-218
2014
6 GAZ-SYSTEM S.A.
LNG terminal in Świnoujście
LNG-F-246
2014
7 GAZ-SYSTEM S.A.
Upgrade of gas infrastructure in northern and central Poland
TRA-F-248
2014
8 AB Klaipedos Nafta
Klaipeda LNG terminal
LNG-F-058
2014
9 AB Amber Grid
Capacity enhancement of Klaipeda – Kiemenai pipeline in Lithuania
TRA-N-238
2015
10 GAZ-SYSTEM S.A.
Upgrade of the entry points in Lwówek and Włocławek on the Yamal-Europe pipeline
TRA-N-276
2015
11 Gasum Oy
Pansio LNG
LNG-N-277
2015
12 PGNiG
PMG Brzeznica
UGS-F-201
2016
13 Swedegas AB
Gothenburg LNG (preliminary)
LNG-N-032
2016
14 Balti Gaas plc
Paldiski LNG Terminal
LNG-N-079
2016
IMPLEMENTATION 2017–2020 15 Manga LNG Oy
Tornio ManGa LNG Terminal project
LNG-N-194
2017
16 AS EG Võrguteenus
Karksi GMS
TRA-N-084
2017
17 Elering
Tallinn LNG Terminal
LNG-N-146
2017
18 Gasum Oy / AS EG Võrguteenus
Balticconnector
TRA-N-023 / TRA-N-072
2018
19 GAZ-SYSTEM S.A. / AB Amber Grid Gas Interconnection Poland-Lithuania (GIPL)
TRA-N-212
2018
20 GAZ-SYSTEM S.A.
North-South corridor in Western Poland
TRA-N-247
2018
21 Gasum Oy
Finngulf
LNG-N-024
2019
22 GAZ-SYSTEM S.A.
PL – CZ interconnection
TRA-N-273
2019
23 GAZ-SYSTEM S.A.
PL – SK interconnection
TRA-N-275
2019
24 Lietuvos Energijos Gamyba AB
Syderiai Underground Gas Storage
UGS-N-034
2019
25 PGNiG
KPMG Mogilnio
UGS-F-200
2020
26 GAZ-SYSTEM S.A.
PL-DK interconnection (Baltic Pipe)
TRA-N-271
2020
27 GAZ-SYSTEM S.A.
Upgrade of the LNG terminal in Świnoujście
LNG-N-272
2020
IMPLEMENTATION 2021 –2023 28 PGNiG KPMG Kosakowo
UGS-F-199
2021
29 AS Latvijas Gāze / AB Amber Grid Enhancement of Latvia – Lithuania interconnection
TRA-N-131
2021
30 GAZ-SYSTEM S.A.
Upgrade of PL – DE interconnection in Lasów
TRA-N-274
2021
31 GAZ-SYSTEM S.A.
North-South Gas Corridor in Eastern Poland
TRA-N-245
2023
32 AS Latvijas Gāze
Modernisation of Inčukalns Underground Gas Storage
UGS-N-130
2025
Table 4.1: Planned infrastructure projects
1) In the project code „F“ means FID, and „N“ non-FID.