City of Morgan Hill Sewer System Master Plan 2017
Table 8.1 Unit Costs
Sewer System Master Plan City of Morgan Hill
PRELIMINARY
Pipelines
Pipe Size
Improvement Type Unit Cost
New/Parallel/Replacement
CIPP
Cleaning
CCTV
(in)
($/unit length)
($/unit length) ($/unit length)
($/unit length)
6
156
24
1.03
1.29
8
171
37
1.03
1.29
10
185
51
1.03
1.29
12
199
64
1.03
1.29
15
270
84
1.03
1.29
18
313
105
1.03
1.29
21
370
125
1.03
1.29
24
426
145
1.03
1.29
27
498
‐‐
‐‐
1.29
30
569
185
‐‐
1.29
36
711
‐‐
‐‐
1.29
Pipeline Casings
22$ per inch diameter per linear foot
Notes :
2/17/2017
1. Unit costs are based on an ENR CCI Index Value of 10,532 (01/2017)
Made with FlippingBook - Online magazine maker