E. WALLBACH (DE/CH)
Similar to the French / Switzerland IP, the interconnection between Germany and Switzerland reached its highest levels in February 2012, in relation to the cold snap, and its maximum in coincidence with additional import needs for Italy (possibly linked to temporary interruptions from North-Africa supplies, such as Libyan gas). Like Oltingue IP, technical capacities are nearly fully booked, with maximum use in case of supply shortages downstream.
10 12 €/MWh
700 GWh/d
IP Wallbach DE > CH
600
0 2 4 6 8
500
400
300
200
100
-4 -2
0
Jan
Mar Feb Apr May Jun Jul
Aug Sep Oct Nov Dec Jan
Mar Feb Apr May Jun Jul
Aug Sep Oct Nov Dec
2012
2013
Daily Flow Range
Technical Firm Capacity Booked Firm Capacity
Price Spread PSV – NCG Average Monthly Flow
Figure 3.19: Technical capacities, booked capacities, gas flows and price spreads at Wallbach IP (DE/CH) (Source: ENTSOG Capacity Map 2014, Fluxys TENP, OGE, FluxSwiss and Swissgas)
Image courtesy of FluxSwiss