ENTSOG GRIP SNC 2014-2023
8.4.2 CASE STUDY 2:
SOUTH-NORTH FLOW (RUSSIAN MINIMIZATION)
When Russian supplies are minimized under average demand situations more gas is needed from other sources. When the SNC projects aimed at creating reverse flow capacity in the corridor would be commis- sioned, additional gas can be delivered from the South towards North and East Europe, adding up to increased flows from the west, and help to compensate for the reduced imports from Russia.
137
171
214 138
CASE DESCRIPTION Year 2023 Demand
Average Day Europe
Supply
Minimization Russia
Infrastructure
FID + non-FID
Figure 8.9: Case study 2: South-North Flow (Russian minimization)
Image courtesy of Fluxys Belgium
96 |
South-North Corridor GRIP 2014–2023
Made with FlippingBook