EC Meeting November 2018
REQUEST FOR INFORMATION SCHEDULE
PROJECT NUMBER: C00363 REVISION 9 DATE: 11/10/2018
PROJECT:-
QUORN GRANGE HOTEL
Outstanding
Resolved
Further Info
Overdue
RFI NUMBER
DETAILS
ISSUED REQUIRED ACTION
RECEIVED
COMMENTS
Confirmation of whether the electric, gas and water services previously planned for the Nursery (now omitted from the scheme) are still required to be installed but left terminated
Confirmed gas, water and ducts for electric and BT still required to be installed, termination location to be set out by architect
C1
09/04/2018
20/04/2018
HMC
24/04/2018 & 25/04/2018
Confirmation of size/capacity requirements for any gas, electric and water services to be installed to the "Nursery" building, what is the planned use in the future Confirmation whether the BT box works near to Wood Lane have been organised, to enable the pole relocation to be arranged Please provide a copy of the agreement signed between the client and the farmer, to establish any specific requirements for the access road Planning conditions discharge P/18/0222/2 condition 3 refers to Ruskin`s Arboricultural Report ref 0316- 1871-Rev 1 and Corstophine & Wright tree removal drawing 17415-0302-P-00 (the tender documents only has drawing 17415-0302-T-00 issued which has some irregularities with the Ruskin report) please issue a copy of P-00 The Ruskin Arboricultural report refers to the employment of an Arboricultural Clerk of Works it is assumed that this role is employed by the client, if so, would you please forward contact details to enable us to make arrangements to comply with planning condition discharge
JTL to calculate capacity for gas, water to omitted Nursery block based on previousc design requirements for Nursery
C2
09/04/2018
20/04/2018
JTL
24/04/2018
C3
09/04/2018
16/04/2018
HMC
24/04/2018
Revised BT scheme to be forwarded by HMC
C4
09/04/2018
16/04/2018
HMC
12/04/2018
Copy of agreement issued
Copy of planning discharges issued together with copy of Corstophine & Wright drawing 17415-0302-P-00
C5
09/04/2018
11/04/2018
HMC
12/04/2018
Clarified subsequently by Corstophine & Wright that the Ruskin report is only mentioned in the context of the drawing identifying what trees are removed and which are to be protected. There is no requirement for an arboricultural clerk of works
C6
09/04/2018
16/04/2018
HMC
24/04/2018 & 25/04/2018
24/04/2018, 18/05/2018, 04/06/2018
C7
Confirmation of temporary GFTU accomodation proposals as Portakabin drawing and layout
16/04/2018
25/04/2018
JTL
All layouts agreed
Confirmation that the alternative gridforce Park 40 product is acceptable to use in the temporary car parking to be formed
C8
23/04/2018
27/04/2018
HMC
25/04/2018
Confirmed acceptable to use
Confirmation of preferred gas meter housing options for new housing/apartments and main incoming supply for hotel Confirmation of foul drainage requirements and positions/locations for the client bar area in reception of the hotel extension Confirmation of whether a gate and link path is required from Wood Lane to the new residential area as nothing shown on tender drawings
Confirmed new housing will have semi concealed brown meter box 1Nr per property and main supply to hotel will be in free standing green kiosk
C9
26/04/2018
01/05/2018
HMC
26/04/2018
C10
18/05/2018
04/06/2018
HMC
18/05/2018
2Nr additional foul connections required
C11
18/05/2018
11/06/2018
HMC
18/05/2018
No gate required
Confirmation that the client is providing a fully detailed landscaping scheme to satisfy Planning Condition Nr 9
All planting by GFTU-note drawing will need to be submitted to planning for discharge of relevant condition
C12
18/05/2018
18/06/2018
HMC
18/05/2018
Discrepancies within ER`s; Internal partitions spec to Hotel Extension
05/07/2018
12/07/2018
HMC
12/07/2018
Confirmed spec to meet building regulation and fire requirements
C13
Discrepancies within ER`s; IPS to Hotel Extension
05/07/2018
12/07/2018
HMC
12/07/2018
Clarified that IPS not required and can be constructed as half height partition
C14 C15 C16 C17
Discrepancies within ER`s; Render to GFTU extensions
05/07/2018 06/07/2018 20/07/2018
12/07/2018 16/07/2018 27/07/2018
HMC HMC HMC
12/07/2018 12/07/2018 20/07/2018
Render confirmed as flat through colour not roughcast
Discrepancies within ER`s; Clarification of dorma`s to Hotel Extension
Dorma finish to be flat through colour render not tile hanging
Confirmation of whether any provision for drainage is required to serve the possible future Nursery There are isolated kerbs in areas that are not for renewal that have been damaged previously by others, do any of these want replacing with isolated new kerbs Quality of existing retained doors in GFTU not suitable for re-use, confirm whether new doors will be instructed
C18
20/07/2018
03/08/2018
HMC
03/08/2018
Clarified how to proceed
C19
20/07/2018
27/07/2018
HMC
03/08/2018
Clarified to fill and redecorate if possible
C20 C21 C22
Setting out position required for 2Nr extra drains in bar area to hotel extension
20/07/2018 18/09/2018 10/10/2018
27/07/2018 15/10/2018 12/10/2018
HMC HMC HMC
20/07/2018 10/10/2018 10/10/2018
Electrical data sheets for lighting fittings etc issued for approval
Approval issued
Through colour render to GFTU confirmed as Weber "Beige"
HMC request confirmation from Corstophine & Wright