EC Meeting November 2018
Ref : MGC/1816/SM5
Date : 15.10.2018
Page 5 of 5
ACTION BY
6.7. Foundations for housing being installed this week.
6.8. J Tomlinson will have separate site manager for houses, with set up on that part of the site.
Post Meeting Note Steven Card
6.9. DI’A reported that Sections 2 and 5 are in delay. However in terms of the final completion date this will be determined by the hotel extension and houses and both are proceeding as per programme.
CONTRACTOR’S REQUEST FOR INFORMATION
7.0
7.1. See RFI tracker and minute 6.6.
FINANCIAL MATTERS
8.0
8.1. Noted that Eco1 have submitted drawings for GFTU office fire alarm and these have been approved. Provisional Sum to be adjusted to reflect this.
MC
8.2. Payment under Notice 4 was slightly short. MC has discussed with GFTU and this will be corrected.
STATUTORY UNDERTAKEN
9.0
9.1. See Contractor’s Report.
ANY OTHER BUSINESS
10.0
10.1. None.
DATE OF NEXT MEETING
11.0
Tuesday 13 th November 2018 at 10.00am