EC Meeting November 2018
Roof tiling
100
100
75
Rainwater goods
100
0
76
External render
100
0
77
Internal walls
100
100
78
Install patresses
100
100
79
Work to fire alarms
100
50
80
First fix electrical
100
100
81
Ventilation/Plumbing
100
50
82
First fix Mech
100
50
83
New doors and frames
100
75
84
Cat 6 containment
100
0
85
Plastering
100
50
86
New dpm ,Insulation ,screed
100
100
87
Make good floors /laytex
100
0
88
IPS framing
100
0
89
Floors to wet areas
100
0
90
Install sanitaryware
100
0
91
Above floor drainage
100
0
92
Ceramic Tiling
100
0
93
IPS paneling
100
0
94
Skirting/arch
100
0
95
Doors and ironmongery
100
0
96
2 nd fix Electrical
50
0
97
Pipework above ceiling
100
100
98
Testing lagging in ceiling
100
0
99
Plasterboard bulkheads to ceiling
100
100
100
Suspended ceiling grids
100
0
101
Lights / vents etc to ceiling
100
0
102
IInstall new base units /tops sinks
100
0
103
Air conditioning
100
0
104
Decorations
100
0
105
Floor finishes
100
0
106
Fixtures and fittings
100
107
Test and commission
100
108
CCTV to drains
100
109
Snagging
110
Buildiong control final inspections
111
Cleaning
112
Document 6 (06/01/17)