EC Meeting November 2018
2.3 Inclement Weather
Days lost in month to Inclement Weather
1
Days
Total days lost to Inclement Weather
1
Days
12/10/18 rain affecting brickwork to hotel structure and groundworks
2.4 Potential Gains
None anticipated
2.5 Matters affecting progress/potential Risks
Completion of M & E design to GFTU training rooms Gas scheme – site wide Severn Trent separate feeds required to GFTU/Nursery?
2.6 Statutory Authority connections
Refer to attached Services Tracker revision 9 dated 11/10/2018 WPD diversion completed and energised Quotations now issued for gas, water but need amending/updating as discussed
Section Three - Clients Instructions/Confirmation of Verbal Instructions
3.1 Clients Instructions Issued
Numbers
1
to
12
Inclusive
Document 6 (06/01/17)