Oil & Gas UK Decommissioning Insight 2014
DECOMMISSIONING INSIGHT 2014
Historical Variation in the Removal Cost per Tonne Forecasts on the UK Continental Shelf
The average forecast cost per tonne for both topsides and substructures has seen a relatively small variation across the last four surveys in the CNS and NNS areas ( Decommissioning Insight Reports 2011 to 2014). Figure 15: Historical Variation in the Removal Cost per Tonne Forecasts for Topsides and Substructures in the Central and Northern North Sea (2011 to 2014 Surveys)
14,000
12,000
10,000
8,000
6,000
4,000
2,000 Estimated Cost per Tonne (£)
0
2011 2012 2013 2014
2011 2012 2013 2014
Topside
Substructure
Average Forecast Topside Removal Cost Per Tonne Average Forecast Substructure Removal Cost Per Tonne Range in Cost Forecasts
Source: Oil & Gas UK
Removal Cost per Tonne
2013 Average
2014 Average
Topsides
£4,100 £4,300
£2,900 £4,300
Substructures
30
Made with FlippingBook Learn more on our blog