Total Collaborative Study Protocol_Solus One Salmonella v1 1
9) After the timeline has been accepted, loading of sample tube racks, reagents and
consumables is initiated.
( c )
Loading the Dynex DS2 Instrument
1) If not already onboard, load sample test tube racks into the slots.
2) Remove the lid from the pipette boxes and load into the instrument.
3) Load the Conjugate, TMB Substrate, and Stop Solution into the correct locations specified
by the instrument.
4) Load the Negative and Positive Controls in each position specified by the instrument.
5) Prepare and dispense the correct amount of Activated Washing Buffer.
6) Verify all disposable containers do not need emptying.
( d ) Remove Samples
1) When the run is completed, open the lid to the Dynex DS2 instrument and remove the
loading trays, with the sample test tubes, by pulling the loading trays out away from the
instrument. Discard sample test tubes in the proper location according to laboratory
procedures.
2) Discard the reagent tubes, negative controls, and positive controls in the proper location
according to laboratory procedures. Note: Reagents may be capped and refrigerated at 2–
8°C with the rest of the remaining kit.
Interpretation and Test Result Report
( a ) Viewing results
1) To view a report on a completed run, select the desired result file in the “Recent Test” Box,
Page 20 of 39