Bundles and towed installation
Bundles and towed installation
53
FLOW-LAY
Surface tow Flowline slung below buoyancy Reusable HDPE pipe as carrier Installed by
Fabric strap with quick release
Reusable HDPE carrier
controlled flooding of line
Carrier straps released
Coated flowline
The system is similar in some respects to ‘flat-pack’ bundles in that the buoyancy is located above the flowline. However, with Land and Marine’s Flow-Lay system, the bundle is towed at the surface and the carrier is recoverable for reuse.
FLOW-LAYINSTALLATION
FLOW-LAY INSTALLATION
Touchdown position controlled using tension of tow tug
Flowline filled from surface through towhead valving
Touchdown monitoring
Flooded portion of flowline
Buoyancy floats to surface and is recovered in sections
Straps released
A pig is used to ensure that the flooding can take place in a controlled manner. The important difference in Flow-Lay is that with modern methods of touchdown survey monitoring, the flowline can be positioned exactly when combined with real-time control of the flooding and tow tug positions. All three vessels are in direct communication with each other. The tow tug can be moved either port or starboard to correct any lateral current on the pipeline.