City of Shakopee Capital Improvement Plan 2018-22

Capital Improvement Plan City of Shakopee, Minnesota

thru 2018 2022

Department Capital Improvements Fund

Contact Public Works Director

Type Improvement

CIF-22-003

Project #

Useful Life

Project Name T.H. 169 Pedestrian Bridge

Category Bridges

Accounting Code

Priority 3 Less Important/Future Cons

Fund Capital Improvement Fund

Description An additional pedestrian bridge east of C.R. 83 over T.H. 169 along PLSLWD channel is needed to complete trail connections. Project is to build a new pedestrian bridge utilizing Federal Aid Highway Funds. Total Project Cost: $3,000,000

Justification For pedestrians or bicyclists to cross T.H. 169 if this is designated a regional trail by Met Council and Scott County.

Expenditures

Total

2018

2019

2020

2021

2022

3,000,000 3,000,000

3,000,000 3,000,000

Construction/Maintenance

Total

Funding Sources

Total

2018

2019

2020

2021

2022

500,000

500,000

Capital Improvement Fund Cost Sharing, MnDOT/Federal

2,000,000

2,000,000

500,000

500,000

Park Reserve Fund

3,000,000

3,000,000

Total