Suitability
KHS InnoPET Blomax Series II with ABB T 200 / CS 31 PLC system
Economic efficiency calculation
Conversions time / Delivery time
Sample calculation:
Delivery time: 8 - 10 weeks after order confirmation
Assumptions: Blomax 16 series II with 21,000 bph Annual production = 5,000 h => 105m bottles per year Profit per bottle = € 0.5 ct Profit loss in the event of PLC breakdown
Installation time: 12 – 14 working
days by two KHS service engineers
(software engineer and electrician)
1% downtime = 50 h (approx. 2 days) => 5,250 € 10% downtime = 500 h (approx. 20 days) => 52,500 €
Additional economic risks for the business: Contractual penalties due to delivery delays! Ongoing production fixed costs through personnel!