Enrico Tomassoli (HOK) Samy Elsayed (Skanska Walsh JV) Frank Corallo (Skanska Walsh JV) Brady Lawler (Skanska Walsh JV) Chung Tia (Skanska Walsh JV) Michael Boland (Skanska Walsh JV) Sean Hickey (Skanska Walsh JV) Douglas Moore (Skanska Walsh JV)

Bolts connecting the brace beams to the gusset plates of the main bridge truss were installed with the nuts being placed on the outer face of the gusset along grid BR and BQ at all the vertical gussets, roof level, refer to photo 1 in the attached report. Bolts were drawn head-side out to minimize the size of the truss enclosure. The orientation was discussed with the contractor during fabrication, and commented on in the shop drawing review. Contractor to reverse the bolt installation to have the head of the bolts located on the outer face of the gusset to match HOK’s design drawing and the approved shop drawing comments from submittal CB-631-05120-07082-R1 on sheet 03-004A.

Description:

HOK Field Observation Report - S005 - 20190131.pdf

Attachments:

View in Procore

Link:

Powered By Procore | support@procore.com | https://support.procore.com

Brian P. Mock (646) 891-9296

From: Sean Sent: Tuesday, February 5, 2019 12:29 PM To: Mock, Brian ; Corallo, Frank Cc: Andee ; Gary ; Zach Subject: Fwd: PBB GFRG Capital