From: Sherry Maleki Sent: Wednesday, June 26, 2019 1:35 PM To: Trause, Zachary ; Mock, Brian

Cc: John Girardi ; Ali Istchenko ; Corallo, Frank ; Bilgen, Murat Subject: RE: GWB substitution for GRG at Truss Enclosures Hi Zach, I tried calling and left you a message. Thank you for sharing the GFRC and GFRG shop drawings, however I need to share the drawings with my Executive team to obtain approval. Please mark-up and highlight the extent you wish to switch from GFRG to GWB. Thanks

Cheers, Sherry Maleki Manager, Architecture and Finishes LaGuardia Airport Terminal B, Room 3801 Flushing, NY 11371 From: Trause, Zachary Sent: Wednesday, June 26, 2019 12:35 PM To: Sherry Maleki ; Mock, Brian

Cc: John Girardi ; Ali Istchenko ; Corallo, Frank ; Bilgen, Murat Subject: RE: GWB substitution for GRG at Truss Enclosures Sherry – within RFI BB-0078, the SWJV follow-up response on 6/5/19 to HOK (see below) has the information and two drawings (attached) showing the extent of the GFRG and GFRC scopes of work. Please advise if any questions, thank you.

Zack Trause Project Engineer

SKANSKA WALSH Design-Build Joint Venture LaGuardia Airport CTB Replacement Project