REA Final - 22 Dec 20 - eBook - 1682 pages

; Rose Subject: CO #7 - Change of wall type at elevator pit All,

Attached is the CO for the installation of the stud framed wall in lieu of poured concrete. This includes the signed tickets, the drawings with dimensions to support footages, and material invoices. As per contract, we included profit on the materials but not the labor. Please review and advise. We would like to add this to the 12/1 - 12/15 draw. Thank you, Sean Reed Project Manager Spearhead Construction, LLC MBE | WBE | SDVOB | SDVOSB | PANYNJ | NYCSBS Sean@SpearheadCx.com Ph: 631.793.7422

The information contained in this email message is legally privileged and confidential information intended solely for the use of the intended recipient(s). If you are not the intended recipient(s), any distribution, dissemination, or reproduction of this email message is strictly prohibited. If you have received this message in error, please immediately reply to the sender and then destroy this message.

Made with FlippingBook - professional solution for displaying marketing and sales documents online