CHANGE ORDER Template

Date:

December 31, 2019

Change Order No.

7

Material

Name

Quantity Needed

Unit Price

Total

6" stud (l.f.) 6" track (l.f.)

227 110

0.897 0.894 30.76 0.577

$203.62 $98.34 $246.08 $130.40

5/8" purple xp 4x10 (ea) Thermafiber insulation (p/sf)

8

226

OH&P (15%) Total amount

$101.77 $780.21

Labor

Unit Cost

Total Cost

Individual or Crew

Hours Needed

10/22/2019  ‐  (8) men (3) hours 11/17/19  ‐  (4) men (4) hours 11/24/19  ‐  (4) men (5) hours 11/24/19  ‐  (2) hours gen foreman

24 16 20

106.89 106.89 106.89 113.67

$2,565.36 $1,710.24 $2,137.80

2

$227.34

OH&P (15%) Total amount

0

$6,640.74

Equipment

Item

Time Needed

Unit Cost

Total Cost

Other

Item

Time Needed

Unit Cost

Total Cost

Sean Reed Project Manager Sean@SpearheadCX.com