REA Final - 22 Dec 20 - eBook - 1682 pages
CHANGE ORDER LaGuardia Airport - Pedestrian Bridge B
Date:
February 18, 2020
To: Skanska Walsh JV Attention: John Dolan
Contact: Sean Reed
Spearhead Construction
Address: Hangar 5A Runway Drive Flushing, NY 11371 Email: John.Dolan@SkanskaWalsh.com
Email: Sean@SpearheadCx.com Office: 631.793.7422
Spearhead Change Order No.
Presidents Day
Scope Affected:
4th floor finish
Description
Total cost of labor for Holiday - Presidents Day - Total value of work performed from recent requisition #19/Draw 102.
President's Day weekend work represents a push primarily in Finishes (Taping)
Reason
As directed by SWJV
Justification and Support Ticket attached
Current Contract Price: (Up to CO #2) Change Order Price:
Projected Scope Workdays:
Change Order Added Workdays:
$129,591
0
Net Workdays:
Net Order Price:
Note: Change Order Price represents value of Premium Time plus value of Contract Work performed ; See page 2 for contract values. Invoice attached with documentation. Thank you.
(Itemized Work Breakdown Follows)
Spearhead Construction, LLC
PO BOX 575 Fort Montgomery, NY 10922
Made with FlippingBook - professional solution for displaying marketing and sales documents online