Daily Report

LGA - 620-027 — LGA CTB Replacement - PBB

Gary Miuccio Spearhead Construction Mobile: 2014709130 Gary@spearheadcx.com

Daily Report No: LGA -

From

620-027-TTYT

Date: 2/17/2020 Time On Site: 7:00 AM Time Off Site: 11:30 PM

Weather: Partly Cloudy Temp: 42°F Wind: Light Breeze

Total Workers: 5

Crew

Hours

Employee / Labor Class Puello, Ruben — 0050HMFin / Journeyman Rodriguez, Carlos — 0063HMFin / Journeyman Milo, Andrew — 0084WM Carp / Journeyman Gilmour, Russell — 0082WMCarp / Journeyman Miuccio, Gary — 0020WMCarp / Superintendent

Work Type

Cost Code

Comments

1x 1.5x 2x Lost Units

5601—TAPING - CEILINGS

Base Contract

0 9 0 0 0 2nd Shift

5601—TAPING - CEILINGS

Base Contract

0 8 0 0 0 2nd Shift

Base Contract

5400—INSTALL - BEADS

0 0 8 0 0 2nd Shift

Base Contract

5400—INSTALL - BEADS

0 0 8 0 0 2nd Shift

5001—SUPERVISION - SUPERINTENDENT

Base Contract

Double Shift

0 0 16 0 0

TOTAL:

0 17 32 0 0

Equipment Usage

Code Equipment

Notes

Hours