The cartoon could be PedBB. I am not making it out to LGA today. I mentioned to Gary yesterday that we need more tapers to move along the areas of installed drywall and turn more areas over to the painters. The Port Authority & LGP, as well as SkanskA executives are touring the Headhouse & Ped Bridge B, since both areas are suppose to submit their formal request to TPTO (Temporary Permit To Occupy), which is contracture obligated to be issued to Port Authority on Friday, March 6, 2020. We need to have Life Safety systems final tests completed and the 4L & 3L looking complete and near ready for the public.

3/1/20, 2 " 33 PM

I’m headed down in about a half hour. re PA and LGP…. I was there on Fri at end of the day and met Larry Gillman. He was with someone from Vantage named Mike. We had a nice conversation. He thought the bridge had turned out really well.