REA Final - 22 Dec 20 - eBook - 1682 pages
May 1, 2020
Frank Corallo, Pedestrian Bridge B Area Manager Skanska Walsh Design-Build JV LaGuardia Airport Hangar 5A Runway Drive Flushing, New York 11371
Re: Response to Spearhead Credit Change Order Request #21 – Back of House Work Project: Subcontract No. 620-027
Mr. Corallo:
Your letter dated May 8, 2020 sent to Ms. Andee Hidalgo has been received.
While we disagree with your assessment, we look forward to reconciling the closeout of our contract.
Sincerely,
Ira Grunther Chief Financial Officer Spearhead Construction, LLC
Cc Sean Szatkowski, John Dolan, Brian Mock, Vince Piscopo, Suzanne Miritello, Andee Hidalgo, Rose Ott, Sean Reed, Robert A. Sesti, Esq.
PO Box 575 * Fort Montgomery * NY 10922
Made with FlippingBook - professional solution for displaying marketing and sales documents online