EXHIBIT “D” Attachment to Agreement No. 1213126J-000.620027, dated July 16, 2018 , by and between SPEARHEAD CONSTRUCTION LLC and Skanska Walsh Design-Build JV for Furnish and Install Building Framing and Partitions for Pedestrian Bridge B at LaGuardia Airport Central Terminal Building Replacement Project, New York, LaGuardia Airport Queens, New York .

PROJECT SCHEDULE

1.

PROJECT SCHEDULE

Subcontractor acknowledges the specific schedule requirements in the Subcontract and Contract Documents and recognizes that TIME IS OF THE ESSENCE FOR THE WORK. It is expected that Subcontractor will perform its Work in accordance with the Project Schedule, as it may be revised and amended from time to time by Contractor. The start and finish dates, activities, activity durations, activity logic/relationships, sequence of work, coordination with contiguous trades, and coordination with Owner’s separate Contractors shall be as set forth in or reasonably implied from the Project Schedule, which, along with the additional information set forth in this Exhibit D , shall serve as the contractual baseline for Subcontractor’s performance. Subcontractor shall provide within thirty days of the Effective Date a detailed Subcontract schedule that is coordinated with and complies with the Project Schedule, this Exhibit D, and the other Contract Documents, achieves the specific target dates and key activity durations set forth therein, and efficiently and timely accomplishes the scope of Work. Subcontractor shall provide necessary crews and resources as required to support the Schedule. See Subcontract Exhibits X, X1, and X Supplements - Site Requirements and Logistics, associated specific logistic plans, and any attachments to this Exhibit D for additional work flow expectations, sequencing requirements, and Schedule nomenclature. Target dates identified below may shift. Subcontractor pricing shall allow for a 60 day shift in start and finish dates without overall impact to Subcontract Price. Subcontractor also acknowledges and agrees that Contractor may direct a re-sequencing of Subcontractor’s major activities in any given area of the Project in order to maintain the overall progress of the DB D&C Work.

Activities identified in the Schedule are general in nature and may not reflect all work activities required for Subcontractor’s scope of Work.

The following is a list of schedule dates for Subcontractor’s Project Work:

Early Start

Finish

Pedestrian Bridge B Structural Steel Erection

October 2018 March 2019

March 2019 April 2019 April 2018 July 2019 May 2019 June 2019 June 2019 June 2019

Level 4 & Roof Metal Decking

Concrete Placement on Metal Decking

April 2019 May 2019 May 2019 June 2019 June 2019 May 2019 June 2019 June 2019 June 2019 June 2019 April 2019

Roof Installation

Curtain Wall – Weld Clips

Install Exterior Framing System Install Sub Base Standing Seam Roof

Spray on Fireproofing

Install Curtain Wall System Install & Build Out Elevator Install & Build Out Escalators

October 2019 September 2019 September 2019 October 2019

Install & Build Out People Walkway

Install GFRC/GFRG Clips, Angles, Hangers, and Attachments to Structural Steel prior to SOFP Install Suspended Gypsum Board Ceiling Suspension System, hangers, and clamps prior to Structural Steel SOFP

May 2019

April 2019

May 2019

Install GFRC & GRFG

May 2019 June 2019

October 2019

Frame Out all of Level 4 and Public Areas

July 2019

Exhibit D, Page 1 of 3

Project Schedule/Milestones

Version 4.0

(02/22/2017 ed. Rev. 0)