REA Final - 22 Dec 20 - eBook - 1682 pages
DocuSign Envelope ID: 7C63BD82-420A-491C-9083-158B7A040299
EXHIBIT “D” Attachment to Agreement No. 1213126J-000.620027, dated July 16, 2018 , by and between SPEARHEAD CONSTRUCTION LLC and Skanska Walsh Design-Build JV for Furnish and Install Building Framing and Partitions for Pedestrian Bridge B at LaGuardia Airport Central Terminal Building Replacement Project, New York, LaGuardia Airport Queens, New York .
PROJECT SCHEDULE
1.
PROJECT SCHEDULE
Subcontractor acknowledges the specific schedule requirements in the Subcontract and Contract Documents and recognizes that TIME IS OF THE ESSENCE FOR THE WORK. It is expected that Subcontractor will perform its Work in accordance with the Project Schedule, as it may be revised and amended from time to time by Contractor. The start and finish dates, activities, activity durations, activity logic/relationships, sequence of work, coordination with contiguous trades, and coordination with Owner’s separate Contractors shall be as set forth in or reasonably implied from the Project Schedule, which, along with the additional information set forth in this Exhibit D , shall serve as the contractual baseline for Subcontractor’s performance. Subcontractor shall provide within thirty days of the Effective Date a detailed Subcontract schedule that is coordinated with and complies with the Project Schedule, this Exhibit D, and the other Contract Documents, achieves the specific target dates and key activity durations set forth therein, and efficiently and timely accomplishes the scope of Work. Subcontractor shall provide necessary crews and resources as required to support the Schedule. See Subcontract Exhibits X, X1, and X Supplements - Site Requirements and Logistics, associated specific logistic plans, and any attachments to this Exhibit D for additional work flow expectations, sequencing requirements, and Schedule nomenclature. Target dates identified below may shift. Subcontractor pricing shall allow for a 60 day shift in start and finish dates without overall impact to Subcontract Price. Subcontractor also acknowledges and agrees that Contractor may direct a re-sequencing of Subcontractor’s major activities in any given area of the Project in order to maintain the overall progress of the DB D&C Work.
Activities identified in the Schedule are general in nature and may not reflect all work activities required for Subcontractor’s scope of Work.
The following is a list of schedule dates for Subcontractor’s Project Work:
Early Start
Finish
Pedestrian Bridge B Structural Steel Erection
October 2018 March 2019
March 2019 April 2019 April 2018 July 2019 May 2019 June 2019 June 2019 June 2019
Level 4 & Roof Metal Decking
Concrete Placement on Metal Decking
April 2019 May 2019 May 2019 June 2019 June 2019 May 2019 June 2019 June 2019 June 2019 June 2019 April 2019
Roof Installation
Curtain Wall – Weld Clips
Install Exterior Framing System Install Sub Base Standing Seam Roof
Spray on Fireproofing
Install Curtain Wall System Install & Build Out Elevator Install & Build Out Escalators
October 2019 September 2019 September 2019 October 2019
Install & Build Out People Walkway
Install GFRC/GFRG Clips, Angles, Hangers, and Attachments to Structural Steel prior to SOFP Install Suspended Gypsum Board Ceiling Suspension System, hangers, and clamps prior to Structural Steel SOFP
May 2019
April 2019
May 2019
Install GFRC & GRFG
May 2019 June 2019
October 2019
Frame Out all of Level 4 and Public Areas
July 2019
Exhibit D, Page 1 of 3
Project Schedule/Milestones
Version 4.0
(02/22/2017 ed. Rev. 0)
Made with FlippingBook - professional solution for displaying marketing and sales documents online