REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Impact of Delayed Start

Compressed Work Duration

Spearhead Lost Productivity

Impact of Delayed Start

Compressed Duration

Spearhead Innovation Blue Banger Hangers Panelmax (2 Carps, not included in bid price)

Inefficient Access to work areas

Loss of Productivity; Lost time

Poor Scaffold Design

Spearhead provided efficient scaffold solution; PM’s inefficient scaffold resulted in lost time, 3-tiered bakers on top of scaffold, and pipe scaffold directly on escalator treads

Spiders

Takes 3.5 mins RT to reach location @ Moving Walkway

Congestion

Loss of Productivity Trade stacking; Overmanning GFRG sat in warehouse for entire month due to congestion on bridge Request to work 2nd shift to alleviate congestion (denied)

Lull, 1 ea

Delays in getting materials and equipment to work areas 3 weeks to hoist last Spearhead lift Delays waiting for repairs to lull

Overtime

Consecutive days of overtime leads to substantial lost productivity

Made with FlippingBook - professional solution for displaying marketing and sales documents online