ENTSOG TYNDP 2017 - Main Report

Figure 4.12 illustrates the status of those common projects according to TYNDP 2015 submission.

7

10

FID in TYNDP 2017 but not in TYNDP 2015 non-FID both in TYNDP 2015 and TYNDP 2017 FID from TYNDP 2015

%

83

Figure 4.12: Status in TYNDP 2017 for the projects submitted to both TYNDPs 2015 and 2017

7

Projects in delay Projects not in delay

42

58

1–2 years 3–5 years > 5 years

%

54

%

39

Figure 4.13: Share of common projects in TYNDP 2015 and TYNDP 2017 by commissioning status

The charts above illustrate the share of those projects for which a delay has been reported regarding their expected commissioning date and the length of this delay. Among the projects without delay, 8 projects have been submitted with an earlier commissioning date More than half of the projects already submitted in TYNDP 2015 have reported experiencing delays since the last edition. Listed below are the main reasons for delays indicated by project promoters: \\ worsened and uncertain market conditions \\ delays in permitting/authorisations from competent authorities \\ lack of coordination between hosting countries/political uncertainties \\ delays in contract award procedure \\ lack of funds/financing \\ delay following findings from concluded pre-feasibility study

154 |

Ten-Year Network Development Plan 2017 Main Report