Project 2013 Advanced

Lesson 7 – Working with Graphics and Web Pages

Project 2013

Steps

Practice Data

1. Select the task or resource to which you want to attach the hyperlink. The task or resource is selected. 2. Right click and select the Hyperlink button. The Insert Hyperlink dialog box opens. 3. Under Link to , select Place in This Document . The Insert Hyperlink dialog box displays available views. 4. Expand the views under Select a view in this project , if necessary. The views are expanded. 5. Select the view you want to appear when the link is clicked. The view is selected. 6. Select the Enter the task or resource ID box, if desired. The Enter the task or resource ID box is selected. 7. Enter the desired task or resource ID. The ID number appears in the Enter the task or resource ID box.

Select the 17 Frame House task.

Click

.

Click

.

Click next to Views , if necessary.

Scroll as necessary and click Resource Usage.

Click in:

.

Type 9.

8. Select OK .

Click

.

The Insert Hyperlink dialog box closes and a Hyperlink icon appears in the Indicators column.

Right-Click Frame House task, point to Hyperlink and click Open Hyperlink . The Resource Usage view appears with the Carpenter resource displayed.

Practice the Concept: Switch back to the Gantt Chart view and right-click the Hyperlink icon for the 17 Frame House task, righ-click to the Hyperlink command on the shortcut menu, and select the Edit Hyperlink command. Add the ScreenTip text Resource usage for carpenter and close all open dialog boxes. Point to the hyperlink to view the ScreenTip.

Close HOUSE19.MPP .