Table

Description of Resource Table

This table contains fields for total and baseline cost, as well as the variance in cost between them. It also displays fields for actual and remaining cost. Shows the difference between the projected cost and the actual cost required to achieve the current level of completion up to the status date or today's date. This table contains fields for type, material label, initials, group, maximum units, standard and overtime rates, cost per use, accrual method, calendar, and resource code. The same as Entry, but does not show the material columns.

Cost

Earned Value

Entry

Entry - Work Resources Entry – Work Material

The same as Entry, but does not show the Max units or the overtime rate.

Export Combines multiple tables – Cost, Entry and Work Hyperlink This table contains fields for hyperlink text, addresses, and sub addresses. Summary This table contains fields for resource group, maximum units, peak resource usage, standard and overtime rates, cost, and work.

Usage

This table contains a field for work data.

This table contains fields for percent complete, as well as total, overtime, and baseline work. It also displays fields for the variance in work, and actual and remaining work.

Work

NOTE If you cannot see all the information in a field, you can adjust the column width by double-clicking its right border.

Procedures

1. Switch to the desired task or resource view. 2. Select the View tab. 3. Click the Tables command. 4. Select the desired table command.