Project 2013 Advanced

Project 2013

Lesson 3 - Evaluating and Distributing Data

Procedures

1. Switch to the desired task view. 2. Enter the project status date. 3. Select the View tab. 4. Click the Table command. 5. Click the More Tables command. 6. Select Earned Value Cost Indicators or Earned Value Schedule Indicators in the Tables list box. 7. Click Apply .

Step-by-Step

View earned value indicators.

If necessary, switch to the Gantt Chart view and enter a project status date of 6/28/16 .

Steps

Practice Data

1. Select the View tab.

Click

.

The View ribbon appears.

2. Click the Tables command. The Table submenu appears.

Click

.

Click

3. Click the More Tables command. The More Tables dialog box opens.

.

Click Earned Value Schedule Indicators.

4. Click Earned Value Cost Indicators or Earned Value Schedule Indicators in the Tables list box. The table is selected.

5. Click Apply .

Click

.

The table is applied to the view and the earned value data appears.

OFFICEPRO, Inc.

Page 61

Made with FlippingBook - Online catalogs