Project 2013 Advanced

Lesson 4 - Finalizing a Project

Project 2013

NOTE When you first copy the data to your new project file, all tasks reflect the original project dates. Once you mark all tasks as 0% complete and remove the constraints, the tasks reflect dates based on the current date. You can change the dates by entering a project start or finish date in the Project Information dialog box. Before you copy final data and paste it into a new project, you should open the Resource Leveling dialog box from the Tools menu and make sure that the Leveling calculations option is set to Manual . The procedure may not work properly if this option is set to Automatic . To view tasks with constraints, select the Constraint Type option from the Group By box on the View ribbon , Data group. To view tasks with deadlines, select the Tasks With Deadlines option from the Filter list on the View ribbon , Data group.

Procedures

1. Switch to the Gantt Chart view. 2. Select the tasks you want to copy.

3. Click the Copy Task button

.

4. Click the New button .

5. Click the Paste button . 6. If a warning box opens, select OK to confirm changes made to task durations. 7. Select all the tasks you copied.

8. Click the 0% Complete button . 9. To remove constraints and deadlines on all copied tasks, select the tasks and

click the Task Information button

on the Task ribbon, Properties group.

10. Select the Advanced tab. 11. To remove all constraints, select As Soon As Possible from the Constraint type list.