Where Are We in the Integration Management Process? (Pages 91-130) Integration Management Process
What is the desired result when this process is done?
Done During Process Group
Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Manage Project Knowledge Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase
nitiating
lanning
xecuting
onitoring
ontrolling
losing
130
Close Project or Phase (Pages 113-114)
Remember, always close a project!
• Finalize all activities across all process groups
– Confirm work is done to requirements – Obtain formal confirmation that contracts are completed – Gain final acceptance of the product
– Complete financial closure – Hand off completed product – Solicit customer’s feedback about the project – Complete final performance reporting – Index & archive records – Gather final lessons; update knowledge base
131
Inputs: Close Project or Phase ( PMBOK ® Guide, Pages 124-126)
Inputs
• Project charter • Project management plan • Project documents • Accepted deliverables • Business documents • Agreements • Procurement documentation • OPAs
See PMBOK ® Guide Page 121 for complete list