TPi October 2012

business & market news

MCA Hire and Thermofuse Pipelines in repair programme

treatment works in Oswestry to the Prescot Water treatment works near Liverpool. LTDM number 3 is bitumen- lined steel that will be pressure jetted. Lines 1 and 2 of the LTDM are unlined cast iron and will be refurbished with polyethylene (PE) using the specialist technique of swage lining, a process applied by Denholm Pipecare. The swage lining technique is where butt welded strings of a liner are drawn through a specialist reducing die to reduce the overall diameter of the PE lining and allow insertion into the host cast iron main. Over a period of time the PE’s elasticity will allow the PE lining to revert to its original diameter, creating a tight fit and maximising the bore of the newly lined cast iron main. The specialist operation of butt fusion welding of the large diameter liner is being carried out by Thermofuse Pipelines. MCA, part of Drain Center, was involved with the Vyrnwy project when trials first started four years ago. It provided a McElroy 1648 specialist large diameter butt fusion machine, and as the project developed, MCA imported an additional brand new McElroy 1648 welding

MCA Hire, Thermofuse Pipelines, Denholm Pipecare and Balfour Beatty Civil Engineering Ltd are helping to maintain an 80km stretch of the Vyrnwy Large Diameter Trunk Main (LDTM), UK, for United Utilities.

Ashley Bentley, MCA hire regional operations manager

The team will be working to repair three existing LTDM’s that run from the water

machine from America to enhance on-the-job performance, which is due to make its first UK site appearance next week. Efficiency on-site is already high. United Utilities set the team a target of eight welds per day, but the team from Thermofuse Pipelines sometimes find themselves completing ten or 11 welds in a day. The maintenance and repair work on the pipelines is part of United Utilities’ 14-year cleaning and maintenance programme to the Vyrnwy LDTM to improve water quality. The Vyrnwy LDTM consists of three parallel pipelines with a total length of around 240km.

Thermofuse case study

MCA Hire Services – UK www.mcahire.co.uk

Contract for 750km Upper Zakum field awarded to Technip

Technip’s operating centre in Abu Dhabi will execute the overall engineering and participate in procurement, on-island works, cable installation and initial production. The project is scheduled to be completed in the third quarter of 2015. The award reinforces Technip’s involvement in major offshore projects and its association with NPCC.

processing facilities at the Central Complex. The scope of work covers 240kmof subsea pipelines ranging from 6" to 42"; 128km of subsea composite and fibre-optic cables; and almost 30,000 tons of offshore structures (jackets, riser platforms, flare towers and bridges), including approximately 3,000 tons of islands modules and bridges. The contract also includes the complete initial production facilities for temporary wells hook up to serve initial production distributed amongst the North, South and Central islands.

Technip, in a consortium with National Petroleum Construction Company (NPCC), has been awarded, by Zakum Development Company (ZADCO), a lump sum engineering, procurement, fabrication, installation, commissioning and start-up contract for the Upper Zakum 750K Project in Abu Dhabi, United Arab Emirates. The field is located in the Gulf, 84km offshore Abu Dhabi. It is divided into four production artificial islands (Central, North, South and West), with

Technip – France www.technip.com

14

Tube Products International October 2012

www.read-tpi.com

Made with