ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
Pansio LNG - Gasum Oy
201
LNG-N-277
Pansio LNG
Non-FID
LNG Terminal
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Gasum Oy
Operator
Gasum Oy
TEN-E Project ?
Not part of TEN-E
Interested by PCI ?
Not defined yet
IGAs
None
Web Link
www.gasum.com
Undefined (100,00%)
Gasum Oy (100%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Regasification facility
Considered TPA Regime
End of permitting phase
Negotiated (e.g. Exemption)
Considered Tariff Regime
FID
Expected volume (bcm/y)
Negotiated (e.g. Exemption)
2014
+0.11
Applied for Exemption ?
Construction
Storage capacity (m3)
No
+30,000.00
Exemption granted ?
Commissioning
Send-out (mcm/d)
Not relevant
2015/4
Last completed Phase :
Ship size (m3)
% Exemption in entry direction
0%
Planned
15,000.00
% Exemption in exit direction
Reloading ability ?
0%
No
Baltic Energy Market Interconnection Plan GRIP 2014–2023 Annex | 53