ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects

Print

Tornio ManGa LNG Terminal project - OutoKompu Oyj

283

LNG-N-194

Tornio ManGa LNG Terminal project

Non-FID

LNG Terminal

SPONSORS

GENERAL INFORMATION

FINANCING

Promoter

ManGa LNG Oy

Operator

ManGa LNG Oy

Outokumpu Oyj (25%)

Others(25%)

TEN-E Project ?

Not part of TEN-E

Interested by PCI ?

Yes

IGAs

None

Web Link

Undefined (100,00%)

RuukkiOyj (25%)

EPV Oyj (25%)

THIRD-PARTY ACCESS REGIME

SCHEDULE

TECHNICAL INFORMATION

Considered TPA Regime

End of permitting phase

Regasification facility

Negotiated (e.g. Exemption)

2013 Q2

Considered Tariff Regime

FID

Expected volume (bcm/y)

Negotiated (e.g. Exemption)

2014

Applied for Exemption ?

Construction

Storage capacity (m3)

Not yet

2014

+50,000.00

Exemption granted ?

Commissioning

Send-out (mcm/d)

Not relevant

2017

+0.00

% Exemption in entry direction

Last completed Phase :

Ship size (m3)

0%

FEED

20,000.00

% Exemption in exit direction

Reloading ability ?

0%

No

Baltic Energy Market Interconnection Plan GRIP 2014–2023 Annex | 59