ENTSOG GRIP BEMIP 2014-2023 / Annex: Infrastructure Projects
Tallinn LNG Terminal - Elering
274
LNG-N-146
Tallinn LNG Terminal
Non-FID
LNG Terminal
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Elering
Operator
Vopak / Elering
TEN-E Project ?
Project of Common Interest
Undefined (30,00%)
Interested by PCI ?
Yes
IGAs
None
Investment, Royal Vopak (50%)
Investment, Elering AS (50%)
Web Link
PrivateFinancing (70,00%)
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
Regasification facility
Regulated
2015 Q2
Tallinn LNG terminal
Considered Tariff Regime
FID
Expected volume (bcm/y)
Regulated
2014 Q3
+4.00
Applied for Exemption ?
Construction
Storage capacity (m3)
No
2015 Q2
+90,000.00
Exemption granted ?
Commissioning
Send-out (mcm/d)
Not relevant
2017/4
+11.00
% Exemption in entry direction
Last completed Phase :
Ship size (m3)
0%
Permitting
75,000.00
% Exemption in exit direction
Reloading ability ?
0%
Yes
PROJECTED CAPACITY INCREASES
Baltic Energy Market Interconnection Plan GRIP 2014–2023 Annex | 61