NOWAL - Nord West Anbindungsleitung

TRA-F-291 Update Date

Project

Pipeline including CS

FID

Advanced

10/05/2016

It is necessary to increase the capacity of the pipeline between the OGE Infrastructure (market area of NCG) and GASCADE (Market area of GASPOOL).This connection will increase the capacity by 6 GW to ensure the supply in south-west Germany.

Description

Regulatory Decisions and similar material conditions

Part of the Nation Development Plan 2016: 083-07, 409-01, 410-01, 411-01

Capacity Increments Variant For Modelling Point

Operator

Year 2017

From Gas System To Gas System Capacity

216.0 GWh/d

GASCADE Gastransport GmbH

DEg

DEn

Comment: Level 1 - Exit Drohne

124.8 GWh/d

GASCADE Gastransport GmbH

2020

DEg

DEn

Comment: Level 2 includes Level 1 in total 340.8 GWh/d -Exit Drohne Comment: Level 3 includes Level 1+2 in total 535.2 GWh/d -Exit Drohne DEn

Drohne GASCADE / OGE

194.4 GWh/d

GASCADE Gastransport GmbH

2025

DEg