Decommissioning Insight 2018
Denmark
1
Figure 24: Well Decommissioning Activity in Denmark
50
Subsea Development Wells
2
45
Platform Wells
40
3
35
30
25
4
20
15
5
10
Number of Wells to be Decommissioned
5
6
0
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Source: Oil & Gas UK
7
Number of Wells
Percentage PlatformWells
132
98%
8
According to the three operators which provided information, well decommissioning activities in Denmark are not expected to begin until 2023, with Danish assets being less mature relative to those on the UKCS. Operators in the sector will therefore be able to use lessons learned from the UKCS, as well as a developed supply chain with considerable work experience to their benefit presenting an opportunity for UK companies to export their expertise.