Permit Report – Critical Dates
Construction Date Goal: 6/8/16
• POs – POs must be issued 10 working days prior to Construction Start Date. • Permit Issued – Time varies for different municipalities. Plans must be uploaded to BuildPro at least 5 days prior to Construction Start Date.