Development:  Site Development – Cresswind Parkway & Model Park Paved. Phase #1 – Sewer 80%, Grading 75%, Storm 0% Cresswind Peachtree Status

 Amenity Site – Padded. Civil submitted.  Lift Station – Complete and accepted

 MacDuff – Scheduled to be to Cresswind Entrance by 8/21/16  CXS Bridge – All approvals acquired. Pre-con ETA 7/1/16  Variance – Final analysis complete. Wynn’s pond engineer reviewing. ETA 7/15/16 Construction:  Home Building – 11 Permits acquired. Homes in various stages.  Welcome Center – Rejected and will be reviewed under commercial. Resubmitted 6/14/16.