LoneRover2
Commercial
Contract for Services
2260 Northwest Parkway • Suite H • Marietta, GA 30067 • 678-290-1325
Date of Issue:
2/1/18
Customer Information
State: GA Steve Hooper Lone Rover Construction Mini Storage Warehouse 2 1225 Canton Road Marietta Jobsite Information
Steve Hooper Lone Rover Construction
Name:
Contact Name:
430 Winkler Drive Alpharetta
Address:
Address:
State: GA
Zip: 30004
Zip: 30062
City:
City:
Phone:
Phone:
Cell: (678) 371-3014
Cell: (678) 371-3014
Fax:
Fax:
shooper@lonerover.com
shooper@lonerover.com
Email:
Email:
ENGINEERED SOLUTIONS OF GEORGIA PROPOSES TO FURNISH AND INSTALL THE FOLLOWING SCOPE OF WORK:
To perform a Structural Repair Program for the purpose of Stabilizing the Settlement Condition occurring at the end of Building H. ESOG recommends the owner to have the adjacent storm drain to be video inspected and have any necessary repairs made.
INSTALL (8) FOUNDATION PIERS: 1. Have utilities marked by locating service. Locating service marks from street to meter. If any private utilities are suspected in the work area, a private locating service must be contracted by owner. ESOG may provide recommendation upon request. 2. Excavate area to expose existing concrete footing. 3. Prep footing and attach galvanized foundation brackets for each pier under center load of footing. 4. Drive foundation piers up to 21’ through poor soil to load bearing strata (Should additional depths be required to achieve the required load capacities an additional charge of $28.00 per vertical foot beyond 21’ shall be added to the contract total if piers advance past 21’).
5. Use foundation piers to raise foundation toward its original elevation 6. Transfer load to piers to stabilize foundation against any further settlement. 7. Secure piers and backfill holes.
PRESSURE GROUT
1. Drill a series of 1.5” diameter holes 5-feet on-center throughout the affected area of warehouse floor. 2. Drive the injection rods through the slab and through poor soil to suitable load bearing strata (estimated average depth of 8’-0”). 3. Force grout under pressure in 12” lifts to compact soil, build grout columns and fill any voids. 4. Estimated grout take is 200 cu. ft. based on industry standard calculations. Final bill will reflect actual grout volume injected into the ground and will be based on $17.33/cu. ft. above or below the estimated volume stated above. The minimum daily charge is $2,900. See terms and conditions on page 2 of this contract for additional information. 5. Apply pressure at the upper lifts and attempt to return slab to a more level position.
6. Patch holes using non- shrink grout. 7. Clean all construction related debris.
Payment Schedule
$4,450.00
Deposit
Total Contract Amount
$17,800.00
$13,350.00
Due Upon Completion
Quotation valid for 30 days from the date of issue. Contract subject to terms and conditions printed on the accompanying addenda.
Presented by ESOG
Accepted by the Customer
ESOG Signature
Date
Customer Signature
Date
Print Name Chuck Irby
Steve Hooper Lone Rover Construction
Print Name
form revision 12/04/12
Made with FlippingBook - professional solution for displaying marketing and sales documents online