Lesson – Tracking Your Progress

Project 2016

7. Continue to change the work values as desired.

Step-by-Step

Enter timephased work values.

Switch to the Task Usage view and apply the Work table. Select the Task Usage Tools Format tab. Check Actual Work checkbox in the Details group. If necessary, drag the split bar so that the timephased details start to the right of the Work field in the table.

Select the 18 Frame House task and use the Scroll To Task button to scroll to the work assignment.

Steps

Practice Data

1. Select the Act. Work field for the assigned resource. The Act. Work field is selected.

Click the Act. Work field in the first T column under

24h for the Carpenter resource (for the date 8/16/18 )

2. Enter the value.

Type 12

The value appears.

3. Press [Enter] .

Press [Enter].

The actual work value is added to the actual work value for the task.

4. Continue to change the work values as needed. The work assignment contour changes accordingly.

Enter 28 hours of actual work for the carpenter for Wednesday thru Friday.

Practice the Concept: Scroll to the week of Aug 20, 18 . For the carpenter, enter 28 hours of actual work for Monday. Enter 20 hours of actual work for Tuesday, which finishes the task.