Project 2016 Intermediate

Project 2016

Lesson – Adjusting Resources

Resource Usage view and the bottom pane displays the Leveling Gantt view. Enter the delay amount in the Leveling Gantt view in the Leveling Delay field. This field is always based on elapsed time. Therefore, if you enter a 7 in this field, a value of 7 days is entered by Microsoft Project, indicating seven elapsed days. If you are using the Standard project calendar, seven elapsed days includes Saturday and Sunday.

The Resource Allocation view

Procedures

1. Switch to the Resource Allocation view.

2. Select the resource name in the top pane associated with the task you want to

delay.

3. Select the Leveling Delay field in the bottom pane for the task you want to delay.

4. Enter the desired delay amount.

5. Press [Enter] .

Step-by-Step

Level a resource by entering a delay amount.