Project 2016 Intermediate

Project 2016

Lesson - Assigning Costs

5. Select the Fixed Cost field for the task to which you want to assign a fixed cost.

6. Enter the fixed cost amount.

7. Press [Enter] .

Step-by-Step

Assign a fixed cost to a task.

If necessary, switch to the Gantt Chart view and apply the Cost table.

Steps

Practice Data

1. Select the Fixed Cost field for the task to which you want to assign a fixed cost. The Fixed Cost field for the task is selected.

Click the 27 Security System task Fixed Cost field for the.

2. Enter the fixed cost amount.

Type 2000.

The value appears in the Fixed Cost field.

3. Press [Enter] .

Press [Enter].

The fixed cost is assigned to the selected task.

Practice the Concept: Assign a fixed cost of $5,400 to the 36 Cabinets task and a fixed cost of $2,500 to the 37 Wood Trim task.

Close HOUSE9.MPP .

OFFICEPRO, Inc.

Page 53