9.3.6.1.1
If swipes or leave requests are missing for a day, an email
should be sent to the supervisor requesting an explanation.
Assigned Schedule versus Managed Schedule 9.4.1 Manage schedule is a day by day adjustment.
9.4
9.4.2 Assigned schedule is where a schedule is assigned at the beginning of a pay period
PRINTED COPIES ARE UNCONTROLLED