ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
PROJECTED CAPACITY INCREASES Interconnection
Capacity (GWh/d)
From Zone
To Zone
Modelled Direction Yes entry
Interconnector SI-HU
38.00
Hub Hungary
Hub Slovenia
DESCRIPTION OF THE PROJECT
Interconnector with the transmission system of the Hungarian TSO.
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional.
COMMENTS ABOUT THE PROJECT FINANCING Public financing
Private financing
Multilateral financing
Southern Corridor GRIP 2014–2023 Annex B |
125
ENTSOG TYNDP 2013-2013 - Annex A
Made with FlippingBook