ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects

UGS - HU - FGSZ/E.ON Hungary PROJECTED CAPACITY INCREASES Interconnection

Capacity (GWh/d)

From Zone

To Zone

Modelled Direction Yes entry Yes exit

189.20 308.00

Hub Hungary

Storage Hungary

Storage Hungary

Hub Hungary

DESCRIPTION OF THE PROJECT

The project aims at enabling a more flexible operation enabling the injectability to be as low as 0.24 Mm3/d.

EXPECTED BENEFITS

Market integration, Diversification of routes.

COMMENTS ABOUT THE PROJECT FINANCING Public financing

Private financing

Multilateral financing

Southern Corridor GRIP 2014–2023 Annex B |

146

ENTSOG TYNDP 2013-2013 - Annex A

Made with