ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects
TRA-N-149
Interconnector Greece Bulgaria - IGB
Non-FID
Pipeline including CS
SPONSORS
GENERAL INFORMATION
FINANCING
Promoter
Public Financing
ICGB a.d.
Not part of TEN-E
TEN-E Project ?
–
Operator
Private Financing
ICGB a.d.
Yes
In PCI list?
–
Multilateral Financing
None
IGAs
–
Web Link
www.icgb.eu
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Considered TPA Regime
End of permitting phase
# of Pipelines, nodes, CS
Negotiated (e.g. Exemption)
2014 Q3
2
Considered Tariff Regime
FID
Total Pipeline Length (km)
Negotiated (e.g. Exemption)
2014 Q3
+182
Applied for Exemption ?
Construction
Total Compressor Power (MW)
Yes
2015 Q1
+10.00
Exemption granted ?
Commissioning
Expected Load Factor
Not yet
2016 Q3
% Exemption in entry direction
Last completed Phase :
Diameter (range) (mm)
–
Planned
DN 800
% Exemption in exit direction
Diameter (range) (inches)
–
32"