FY2021 Adopted Budget
Capital Project Summary
Capital Project Number: WS1102
Activity #: 81782.3999.01
Capital Project Title: DUSWM Maintenance Systemics - Small Systems Wastewater
Region: Countywide
Capital Project Status: Active Asset Type: Maintenance Asset Category: Water & Sewer
Year Identified: 2019 Est Completion Date: 6/30/2026
Capital Project Description: This project anticipates maintenance/systemic needs required for aging County wastewater systems outside the Ballenger-McKinney WWTP service area. These regional systems are considered "small systems": roof replacement, pavement repair/replacement, generator repair/replacement, building envelope improvements such as door and window replacements, pump repairs/replacements, plant and pump station controls/PLC replacement/upgrades, treatment works piping and equipment repair/replacement, low pressure sewer system replacement/upgrades. Current priorities are evaluation and repairs to the Point of Rocks and Crestview WWTPs and the Knoxville low pressure sewer system.
Cash Requirement Schedule:
Project Total
Prior Budget
Categories
2021
2022
2023
2024
2025
2026 Costs After
Architect/Engineering 1,017,750 264,000 128,750 125,000 125,000 125,000 125,000 125,000 Construction - County Funded 2,722,500 1,215,000 257,500 250,000 250,000 250,000 250,000 250,000 Overhead 176,300 116,000 10,300 10,000 10,000 10,000 10,000 10,000 Total Cost: 3,916,550 1,595,000 396,550 385,000 385,000 385,000 385,000 385,000
Funding Schedule:
Project Total
Prior Budget
Categories
2021
2022
2023
2024
2025
2026 Costs After
Trans from W/S Cash Fund
3,916,550 1,595,000 396,550 385,000 385,000 385,000 385,000 385,000 3,916,550 1,595,000 396,550 385,000 385,000 385,000 385,000 385,000
Total Cost: