2027-31 Capital Improvement Plan

Community Center Rooftop Unit Project Name Community Center Rooftop Unit Project # BA-27-003

Total Project Cost $30,000

Assistant City Administrator

Contact

Building Internal Service Fund

Community Center

Department

Type

Recreation

1 - Have to do

Category

Priority

Active

15 years

Status

Useful Life

Building Asset IS Fund

Fund

Description Replacement of an HVAC rooftop unit at the Community Center.

Justification There are 12 total rooftop units at the Community Center, and they will all be reaching the end of their useful life. Replacement of these units will decrease long-term maintenance costs and improve energy efficiency.

Expenditures

2027

2028

2029

2030

2031

Total

Equip/Vehicles/Furnishings

30,000

0

0

0

0

30,000

30,000

0

0

0

0

30,000

Total

Funding Sources

2027

2028

2029

2030

2031

Total

Building Internal Service Fund

30,000

0

0

0

0

30,000

30,000

0

0

0

0

30,000

Total