2027-31 Capital Improvement Plan

Community Center Air Handler Project Name Community Center Air Handler Project # BA-30-002

Total Project Cost $100,000

Assistant City Administrator

Contact

Building Internal Service Fund

Community Center

Department

Type

Recreation

1 - Have to do

Category

Priority

Active

15 years

Status

Useful Life

Building Asset IS Fund

Fund

Description Replace water heaters and air handling units at the community center.

Justification During the community center renovation most of the air handler units were replaced, but not all. Those remaining will have reached the end of their useful life, as will have the water softeners.

Expenditures

2027

2028

2029

2030

2031

Total

Equip/Vehicles/Furnishings

0

0

0

100,000

0

100,000

0

0

0

100,000

0

100,000

Total

Funding Sources

2027

2028

2029

2030

2031

Total

Building Internal Service Fund

0

0

0

100,000

0

100,000

0

0

0

100,000

0

100,000

Total