2027-31 Capital Improvement Plan

Valley View Drainage Project Name Valley View Drainage Project # Storm-30-005

Total Project Cost $93,000

City Engineer Improvement 3 - Want to do

Contact

Storm Drainage Fund Storm Sewer/Drainage

Department

Type

Category

Priority

Active

Surface Water Fund

Status

Fund

Description Drainage improvements to improve sidewalk safety. A feasibility study was completed by AE2S. This issue may be addressed through development of adjacent undeveloped properties. An AUAR has been completed for this area.

Justification There is a large drainage area that is concentrated to a drainage path that flows over a sidewalk and onto the adjacent street. There is a safety concern during the winter when ice builds up in this area and on the sidewalk.

Expenditures

2027

2028

2029

2030

2031

Total

Construction/Maintenance

0 0

0 0

0 0

83,000 10,000

0 0

83,000

Engineering/Administration

10,000

0

0

0

93,000

0

93,000

Total

Funding Sources

2027

2028

2029

2030

2031

Total

Storm Drainage Fund

0

0

0

93,000

0

93,000

0

0

0

93,000

0

93,000

Total

Produced Using Plan-It CIP Software