2027-31 Capital Improvement Plan
City of Shakopee 15-YR Capital Improvement Plan (2027-2041) FINAL October 23, 2026
Large City
Project Number
(CIF) Capital
Grant Funding
Special
Assistance and
SPUC Sanitary Sewer Storm Drainage
Park
Park Asset
Building Internal
EDA
Total Project
Project
Improvement Fund
Assessments
MSA Fund
(Watermain)
Fund
Fund
Development
Fund
Service Fund Revenue Fund
Cost
NOTES
2036
Annual Pavement Rehabilitation Annual Bituminous Mill and Overlay Annual Trail Rehabilitation (along roadways) 2036 Full Depth Pavement Reconstruction 2037 Full Depth Pavement Reconstruction Annual Pavement Reclamite
CIF-36-TBD CIF-36-TBD CIF-36-TBD CIF-36-TBD CIF-36-TBD CIF-37-TBD
$300,000 $4,235,000 $180,000 $150,000 $3,090,000 $300,000
$300,000 $5,450,000 $180,000 $150,000 $4,350,000 $300,000
$1,100,000
$25,000
$30,000
$60,000
$1,140,000
$0
$30,000
$30,000
$60,000
Trunk Sewer Extensions
Sewer-36-001
$217,000
$217,000
Annual Native Vegetation Management Annual Erosion/Pond Cleaning/Outlet Imp Annual Drainage and Flood Prevention Imp Public Works Surface Water: Skidsteer Loader
Storm-36-TBD Storm-36-TBD Storm-36-TBD Storm-36-TBD Storm-36-TBD
$125,000 $200,000 $120,000 $12,700 $14,800
$125,000 $200,000 $120,000 $12,700 $14,800 $101,000 $24,000 $120,000 $180,000 $60,000 $180,000 $29,000 $80,000 $110,000 $240,000 $20,000 $17,000 $17,000
Public Works Surface Water: UTV
Annual Trail Reconstruction Annual Fence Replacement Annual Parking Lot Rehabilitation
PA-36-01 PA-36-02 PA-36-TBD PA-36-TBD PA-36-TBD PA-36-TBD BA-36-001 BA-36-TBD BA-36-TBD BA-36-TBD BA-36-TBD BA-36-TBD
$101,000 $24,000 $120,000 $180,000 $60,000 $180,000 $29,000
Annual Playground Equipment and ADA Improvements PA-36-TBD
Annual Playground Court Resurfacing Green Meadows Plaground and Furnishings Lions Park Rhapsody Music Equipment
Misc Building Improvements Fire Station #1 Boilers Fire Station #2 Rooftop Units 500 Gorman Bldg. Water Softener 500 Gorman Bldg. Rooftop Unit
$80,000 $110,000 $240,000 $20,000 $17,000 $17,000
Library Water Heater
$12,597,500
2036 Subtotal
$8,255,000
$0
$1,140,000
$1,100,000 $4,022,032 $2,922,032
$55,000
$277,000
$592,500
$0
$694,000
$484,000
$0
1/1/36 Balance Avail
12/31/36 Balance Remaing
2037
Annual Pavement Rehabilitation
CIF-37-TBD CIF-37-TBD CIF-37-TBD CIF-37-TBD CIF-38-TBD
$300,000 $190,000 $345,000 $4,495,000 $350,000
$300,000 $190,000 $345,000 $9,610,000 $350,000
Annual Trail Rehabilitation (along roadways)
Annual Pavement Reclamite
2037 Full Depth Pavement Reconstruction 2038 Full Depth Pavement Reconstruction
$2,350,000
$2,500,000
$65,000
$65,000
$135,000
Trunk Sewer Extensions Jetter Truck (Freightliner)
Sewer-37-00=1 Sewer-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD Storm-37-TBD
$221,000 $626,000
$221,000 $626,000 $125,000 $200,000 $122,000 $26,900 $13,000 $133,000 $103,000 $25,000 $122,000 $183,000 $61,000
Annual Native Vegetation Management Annual Erosion/Pond Cleaning/Outlet Imp Annual Drainage and Flood Prevention Imp Public Works Surface Water: Skidsteer Loader Public Works Surface Water: Tractor 3 Point Front PTO
$125,000 $200,000 $122,000 $26,900 $13,000 $133,000
Annual Trail Reconstruction Annual Fence Replacement Annual Parking Lot Rehabilitation
PA-37-01 PA-37-02 PA-37-TBD
$103,000 $25,000 $122,000 $183,000 $61,000
Annual Playground Equipment and ADA Improvements PA-37-TBD
Annual Playground Court Resurfacing
PA-37-TBD
Misc Building Improvements
BA-37-001
$80,000
$80,000
$12,835,900
2037 Subtotal
$5,680,000
$0
$2,350,000
$2,500,000 $5,862,032 $3,362,032
$65,000
$912,000
$754,900
$0
$494,000
$80,000
$0
1/1/37 Balance Avail
12/31/37 Balance Remaing